We have agreed on SCADA System Procurement, Installation, Testing and Commissioning Works for following metro projects with “Aga Enerji Nak. Mad. İnş. San. ve Tic. A.Ş.” ;

  • İkitelli – Ataköy Metro Line (M9),
  • Bakırköy İDO – Bahçelievler – Kirazlı Metro Line (M3)
  • Başakşehir – Kayaşehir Metro Line (M3)

Projects in summary;

İkitelli – Ataköy Metro Line (M9):

  • The line consists of 11 underground passenger stations.
  • The scope of the project includes the revision of the existing 11 stations on M3 Kirazlı – Olimpiyat – Başakşehir metro line.
  • Integration with the existing M3 line will be provided at İkitelli Sanayi Station.

Bakırköy İDO – Bahçelievler – Kirazlı Metro Line (M3):

  • The line consists of 7 underground passenger stations.
  • Integration with the existing M3 line will be provided at Kirazlı Station.

Başakşehir – Kayaşehir Metro Line (M3):

  • The line consists of 4 underground passenger stations.
  • Integration with the existing M3 line will be provided at Metrokent/Başakşehir Station.

At the end of these three projects, M3 and M9 lines will consist of 33 stations and the management of the two lines will be carried out through a single SCADA system.