İstanbul / Kadıköy-Kartal-Kaynarca Metro Line (M4)

PROJECT DETAILS

Within the scope of this project, SCADA system has been designed for all sub-systems of metro line with 19 underground stations including power, environmental and station equipments.

  • 19 Underground Stations, 2 Power Center, 1 Storage
  • Total Tunnel Length: 25 km
  • 44 Hot Redundant PLC Controllers (GE – RX3i)
  • More than 150.000 I/O
  • ECS, CER ve SCADA Control System
  • SCADA Details;
    • Aprx. 250 Environmental Control Screen
    • Aprx. 100 Energy Monitoring Screen
  • Redundant SCADA Server
  • WinCC Open Architecture SCADA
PROJECT SUMMARY
Contract / Project Name Kadıköy – Kartal – Kaynarca Metro Line SCADA System
Project Start Date January 2012
Project Finish Date June 2015 (First Part) – October 2016 (Second Part)
Project Role Sub-Contractor
Project Category Metro Line SCADA System
Location İstanbul / TÜRKİYE