PROJECT DETAILS

Within the scope of this project, SCADA system has been designed for all sub-systems and power equipments in 10 transformer stations.

  • 22 Passenger Stations
  • 10 Transformer Stations
  • Total Length: 15,3 km
  • PLC Controllers (Mauell)
  • More than 7.500 I/O
  • PCS SCADA Control System
  • Redundant SCADA Server
  • WinCC Open Architecture SCADA
PROJECT SUMMARY
Contract / Project Name Topkapı – Habipler Tram Line SCADA System
Project Start Date January 2012
Project Finish Date June 2015
Project Role Sub-Contractor
Project Category Tram Line SCADA System
Location İstanbul / TÜRKİYE