Within the scope of this project, SCADA system has been designed for all sub-systems and power equipments in 8 transformer stations

  • 8 Passenger Stations
  • PLC Controllers (ABB – AC 500)
  • More than 7.500 I/O
  • PCS SCADA Control System
  • Redundant SCADA Server
  • WinCC Open Architecture SCADA
PROJECT SUMMARY
Contract / Project Name İzmir Karşıyaka Tram Line SCADA System
Project Start Date November 2015
Project Finish Date 2018
Project Role Sub-Contractor
Project Category Tram Line SCADA System
Location İzmir / TÜRKİYE